Two water service replacements next week will require temporary road closures on Cliff Street, in the Post Franklin neighborhood.
No water shutoffs are necessary during this work. The area and time required could change due to unforeseen circumstances once work begins. We appreciate everyone’s patience.
Work boundaries and detours are as follows:
Monday, Oct. 31
Cliff Street – Illinois Street to Euclid Avenue
Planned closure for about eight hours, Monday only
Detour: Use Illinois or Euclid, and Lathrop Avenue
Tuesday and Wednesday, Nov. 1 and 2
Cliff Street – Main Street to Elm Street
Planned closure Tuesday and Wednesday
Detour: From Elm, use Mary and Main streets; from Douglas Street, use Midway Court or Lathrop and