Sanitary sewer maintenance work
BATTLE CREEK, Mich. — Routine maintenance of the city’s sanitary sewer system will begin on Monday, February 17.
City contractor, Insituform Technologies, will start sanitary sewer maintenance at the intersection of Jackson Street and Bedford Road beginning Monday.
The contractor will work 24/7 and work should be complete by Monday, March 2, weather permitting.
All work will take place in public rights of way, and in sanitary sewer easements. Disruption to neighbors will be minimal, and streets will remain open to traffic, although, there may be some temporary lane closures.
Please use caution driving through these areas. We appreciate everyone’s patience during these work times.
###